Kember Design Team – Week 38 Report

Prepared by Kember HCM Office · Weeks 35–37 data not available — no week-over-week comparison this period
PART 1 — Productivity
1. Overview (YTD 2026)
No# Units Complete 2026 (IMOS)
5,548
No# Units 2026 (Real productivity)
10,672

2. Weekly Output (Week 38)
New drawing units (IMOS)
226
Revised units (Redline & OP)
150.5

3. Weekly Ranking (Week 38)
1
Lyli Mai (Designer 3)
81
pts
2
Vanessa Vu (Designer 1)
76
pts
3
Lia (Designer 5)
71
pts
4
Henry (Designer 6)
62
pts

4. Productivity per Designer (Week 38)
IMOS new drawings Revised (Redline & OP)
Lyli Mai (D3)
IMOS
47
Revised
33.5
Vanessa Vu (D1)
IMOS
37
Revised
39
Lia (D5)
IMOS
40
Revised
31
Henry (D6)
IMOS
39
Revised
23
Harly Nguyen (D2)
IMOS
38
Revised
4
Mita (D7)
IMOS
25
Revised
20
Tony (D4)
IMOS
0
Revised
0

5. Daily Average (6 days/week)
🥇 Lyli Mai
Designer 3
13.4 units/day
7.8 IMOS + 5.6 Revised
🥈 Vanessa Vu
Designer 1
12.7 units/day
6.2 IMOS + 6.5 Revised
🥉 Lia
Designer 5
11.8 units/day
6.7 IMOS + 5.2 Revised
4. Henry
Designer 6
10.3 units/day
6.5 IMOS + 3.8 Revised
5. Mita
Designer 7
7.5 units/day
4.2 IMOS + 3.3 Revised
6. Harly Nguyen
Designer 2
7.0 units/day
6.3 IMOS + 0.7 Revised
37.7
IMOS avg/day (team)
25.1
Revised avg/day (team)
9.0
Avg/person/day

PART 2 — Design Errors
1. KPI Overview
Error types
7
Confirmed error units
16u
Severity range
Low–Med
Designers involved
5

⚠️ Tony (Designer 4): 0 IMOS / 0 Revised — root cause identified this week
Every project row logged for Tony shows 0 qty this week (1304 India Street, 1950 India, 1950 India Street, 321 Florida St, 700 Colorado, Amsterdam Walk BLDG B1, Avalon San Ramon, The Carina, The Dean, The Massimo, UTA Mixed Use). Four of these carry an explicit note: "Thông tin ban đầu chưa được David kiểm tra" (initial info not yet checked by David) and/or Missing Detail Cabinet input data — e.g. 1304 India Street ("Ruby chưa dim tường"), 1950 India ("sửa theo note của Ruby, David chưa kiểm tra" — Med severity), The Carina ("không tìm thấy thông tin David note").

This is the first week with a documented reason: Tony appears genuinely blocked waiting on David/Ruby to check initial project info across multiple projects, not simply disengaged. Recommend prioritizing David's review queue for Tony's assigned projects.
2. Design Error Types (excludes client-driven redline changes)
🔧 Others / Khác (general fixes)
~48%Low–Med
16u confirmed (+2 unquantified) · Designers: Lia (×5), Mita (×6) · Checker: Tony
Projects: Avalon San Ramon (Med — missing dims, wrong bath size, missing section code, outdated date), Cresent Heights Nema (×2), UTA Mixed Use (×2), 1950 India closet
Notable: one instance cites an IMOS library export bug ("Xuất đen Knife lỗi thư viện imos") — a software issue, not a drawing mistake.
🆕 Missing Detail Cabinet input data
RECURRINGLow
0u confirmed (4 unquantified instances) · Designers: Lyli (×2), Tony (×2)
Projects: Cresent Height Nema, 1304 India Street, The Carina, plus one unnamed Lyli project
This type first appeared in Week 34 (Lyli, once) — now recurring 4x across 2 designers. Worth formally tracking as a standing category rather than "new."
🔧 Others / Source data not yet checked by David
~13%Low–Med
0u confirmed (3 unquantified instances) · Designers: Tony (×2), Vanessa (×1) · Checker: David
Projects: 1950 India, Cresent Hight Nema — see flag above; this is the direct cause behind Tony's zero output this week.
📋 Drawing does not match requirements
~9%Low
0u confirmed (2 unquantified instances, combined with dim issues) · Designer: Vanessa · Checker: Tony
Projects: Amsterdam Walk BLDG B1, The Carina (Main Place Mall Parcel 3)
📐 Vẽ sai tỷ lệ (Incorrect drawing scale)
RECURRINGLow
0u confirmed (1 unquantified instance) · Designer: Vanessa · Checker: Tony
Project: 1950 India Street
Second occurrence for this subtype — both times traced to Vanessa (first seen Week 34, Village at Spanish Oak). Worth a targeted check on scale-setting workflow for her.
🏷️ Missing typical details
~4%Low
0u confirmed (1 unquantified instance) · Designer: Vanessa · Checker: Ryby
Project: 1950 India closet
📐 Missing overall dim / overlapping dim lines
~4%Low
0u confirmed (1 unquantified instance) · Designer: Vanessa · Checker: Tony
Project: The Dean

3. Changes per Redline Request — not designer errors
🔄 Changes per redline request
26 instances (units not individually quantified) · Designers: Lia (9), Lyli (8), Vanessa (7), Mita (2) · Checker: David, Ryby
Projects: spread across nearly every active project (UTA Mixed Use, The Carina, Amsterdam Walk, 700 Colorado, The Dean, Cresent Heights Nema, etc.)
Harly and Henry logged zero redline-driven changes this week. These are client/PM-driven changes — tracked separately from QA error metrics.

4. Highlights

5. Zalo Message Preview
KD
Kember Design Team
📋 KEMBER DESIGN TEAM – WEEK 38 REPORT PART 1 — PRODUCTIVITY 1. Overview (YTD 2026) • No# Units Complete: 5,548 • No# Units (Real Productivity): 10,672 2. Weekly Output • New Drawing (IMOS): 226 • Revised (Redline & OP): 150.5 3. Weekly Ranking 🥇 Lyli Mai (D3): 81 pts 🥈 Vanessa Vu (D1): 76 pts 🥉 Lia (D5): 71 pts 4️⃣ Henry (D6): 62 pts 4. Productivity per Designer (IMOS | Revised) • Lyli Mai: 47 | 33.5 • Vanessa Vu: 37 | 39 • Lia: 40 | 31 • Henry: 39 | 23 • Harly Nguyen: 38 | 4 • Mita: 25 | 20 • Tony: 0 | 0 5. Daily Average 🥇 Lyli Mai: 13.4 u/day 🥈 Vanessa Vu: 12.7 u/day 🥉 Lia: 11.8 u/day Team: 37.7 IMOS/day, 25.1 Revised/day, 9.0 u/person/day PART 2 — DESIGN ERRORS ⚠️ Tony (D4): 0 output this week — traced to "info not yet checked by David" and Missing Detail Cabinet data blockers across 4 projects. 🔧 Others / Khác (~48%) · 16u · Low–Med — Lia, Mita 🆕 Missing Detail Cabinet input data (recurring, 4th–5th time) · unquantified · Low — Lyli, Tony 🔧 Others / Source data not checked by David (~13%) · unquantified · Low–Med — Tony, Vanessa 📋 Drawing does not match requirements (~9%) · unquantified · Low — Vanessa 📐 Incorrect drawing scale (2nd occurrence, both Vanessa) · unquantified · Low 🏷️ Missing typical details (~4%) · unquantified · Low — Vanessa 📐 Missing overall dim (~4%) · unquantified · Low — Vanessa 🔄 26 redline-driven changes this week (not errors) — Lia, Lyli, Vanessa, Mita. Harly and Henry: none this week.